Essar Bulk Terminal wins green nod for LNG terminal

26 October 2020

Essar Bulk Terminal Ltd., a unit of Essar Ports Ltd., has won approval from a key environment clearance agency to build a Rs 2,000-crore liquefied natural gas (LNG) terminal at its port located at Hazira in Gujarat’s Surat district. 

Essar Ports Ltd. is the port operating unit of Ruias’ promoted Essar Group.

The expert appraisal committee (EAC) has recommended the project to the Ministry of Environment, Forest and Climate Change for grant of environmental and coastal regulation zone (CRZ) clearance, according to a document seen by BusinessLine.

Essar Bulk Terminal runs a captive deep-draft port at Hazira from a berth length of 1,650 m and 7 km of navigation channel for handling bulk and break-bulk cargo.

The port operating company has received environment and CRZ clearance in 2014 for expanding the Hazira facility by 4,800 m of berth length with a back-up storage yard.

The planned expansion covers container and breakbulk berth (1,100 m), general cargo (700 m), liquid cargo (500 m) for the handling of petroleum products and chemicals, bulk berth (700 m), offshore support vessel berth (500 m), dry dock and ship repair jetty (700 m) and trestle berth of 600 m.

EBTL has also received permissions for extending the navigational channel from 6.2 km to 17.6 km and deepening the channel from 8 m to 16 m with broadening to 300-350 m and reclamation of 334 hectares of land.